Project Description
PPA CONTROLL, a.s. implemented the following activities in the construction of the tunnel (5 km):
Commissioning in 06/2003
-
Design of CRS project documentation
-
Supply of a central control system (36 control automatic machines)
-
Coordination of suppliers of technological units
-
Design, delivery and assembly of electronics, control elements and communication elements of the traffic control system and variable traffic signs (176 variable traffic signs and 28 traffic lights)
-
Implementation of optical and telephone networks
-
Project documentation and implementation of computer networks
-
Design and implementation of physical measurements
-
Connection to the motorway information system
-
Implementation of the control centre in SSÚD Beharovce